- Contract
- 25SYMV018018778
- Date
- 27.11.2025
- Contractor
- ΔΑ.Σ.Ε. 'Η ΑΓΙΑ ΠΑΡΑΣΚΕΥΗ' ΚΥΨΕΛΗΣ
- Budget (excl. VAT)
- 16,1 K €
- Awarding procedure
- Direct award
- Contracting authority
- Municipality of Kastoria
- Awarding unit
- Technical Service
- Areas of intervention
- Regional Unit: Kastoria
- Amendments to original contract
- no
- Status
- completion unknown: no record of the works’ completion was found in ΚΗΜΔΗΣ or Διαύγεια
On the map: the regional unit derived from the awarding unit is shaded and the dot is the unit's seat where the registry knows it. Named work sites are not recorded for forest co-op contracts.
Timeline Methodology
Document trail
| date | type of document | document code | title | |
|---|---|---|---|---|
| 31.10.2025 | Primary request | 25REQ017834476 | Εργασίες αποχιονισμού Δ.Ε. Μακεδνών (Α.Μ. 84/2025) | |
| 31.10.2025 | Commitment approvalcancelled | 25REQ017877359 | Εργασίες αποχιονισμού Δ.Ε. Μακεδνών (Α.Μ. 84/2025) | |
| 20.11.2025 | Call / notice | 25PROC017974250 | Εργασίες αποχιονισμού Δ.Ε. Μακεδνών (Α.Μ. 84/2025) | |
| 26.11.2025 | Award | 25AWRD018015237 | Eργασίες αποχιονισμού Δ.Ε Μακεδνών | |
| 27.11.2025 | Contract — this document | 25SYMV018018778 | Εργασίες αποχιονισμού Δ.Ε. Μακεδνών (Α.Μ. 84/2025) | |
| 09.06.2026 | Payment order | 26PAY019184575 | 1.651,85 € |
1 live payment orders · 1,7 K € paid
Procurement details of 25SYMV018018778
| date | type of document | document code (ΑΔΑΜ) | title | contracting authority | operating unit | signer | funding |
|---|---|---|---|---|---|---|---|
| 27.11.2025 | Contract | 25SYMV018018778 | Εργασίες αποχιονισμού Δ.Ε. Μακεδνών (Α.Μ. 84/2025) | Municipality of Kastoria | Technical Service | ΑΘΑΝΑΣΙΟΣ ΡΗΜΟΣ - Αντιδήμαρχος | — |
- Registry type
- Υπηρεσίες
- Legal framework
- ν.4412/2016 - Βιβλίο Ι – κάτω των ορίων
- Registry duration
- 6 27.11.2025 → 30.04.2026
Items
| item | quantity | net € |
|---|---|---|
| Εργασίες αποχιονισμού | 335 Ώρα | 16,1 K € |
Extracted quotes from documents
CPV codes
- 90620000-9 Υπηρεσίες εκχιονισμού